Order custom cycling kit three to four months before you need it. Production takes 7–9 weeks once the design is signed off — and before that come design rounds and size collection, which is where most clubs lose their buffer. This guide works the timeline backwards so your kit arrives before your first start line, not after it.

Work backwards from your first race

The maths is simple: 7–9 weeks of production after final sign-off, 1–3 weeks of design rounds before that, and 1–2 weeks to collect sizes from your riders. Add shipping and a safety margin and you land on 13–17 weeks — three to four months — between first contact and kit in hands.

None of those stages is padding. Design rounds take as long as your slowest decision-maker; size collection takes as long as your least responsive member. The production window is the one part you can plan around — the rest is yours to manage.

A month-by-month plan for a spring season

For kit you want in March, start in November. November: send your brief and request a quote. December: design rounds — concepts, revisions, final sign-off before the holidays. January: collect sizes and place the order. February–March: production. Late March: delivery, with your first races still ahead of you.

Shift the whole ladder to match your own season start. The shape stays the same; only the anchor date moves.

Racing to an event deadline?

For a fixed event date, count back 13–15 weeks and treat that as your commit date. Keep a two-week buffer for shipping and the unexpected — a buffer you never need costs nothing, and one you do need saves the event.

If you are inside that window, tighten the variables you control: fewer design rounds, one person with sign-off authority, sizes collected in a single week with a hard deadline. Tell us the date in your brief — we will tell you honestly whether it is achievable before you commit.

Where clubs lose weeks

Almost every late kit order loses its time in the same three places: design feedback that waits for a committee, size collection that drags for a month, and payment collection that blocks the order. A signed-off design that sits in an inbox for two weeks costs exactly two weeks.

The fixes are organisational, not technical: nominate one design owner with the final word, set a one-week sizing deadline, and collect sizes and payment together.

The reorder shortcut

Reorders skip the slow part. Your design stays on file, so there are no design rounds and no redesign risk — new members and seasonal top-ups go more or less straight to production. That turns a three-to-four-month project into roughly the production window alone.

With minimums from 5–10 pieces, a mid-season reorder for a handful of new riders is a normal order, not a special request.

FAQ

How long does custom cycling kit take? 7–9 weeks of production after design sign-off, plus design rounds and size collection before that — 13–17 weeks end to end.

When should we order winter kit? In summer. The timeline is the same; only the season changes.

Can it go faster? Sometimes — fewer design rounds and a single decision-maker are the biggest levers. Tell us your deadline and we will give you a straight answer.

What is the minimum order? From 5–10 pieces depending on the product — reorders included.

The bottom line

Three to four months out, the timeline is comfortable; inside nine weeks, it is a conversation about trade-offs. Tell us your brief and your date, and we will take it from there: request a quote.

DTR — performance cycling and triathlon apparel, designed and developed in Ukraine.

Reading next

Leave a comment

This site is protected by hCaptcha and the hCaptcha Privacy Policy and Terms of Service apply.